Last changed in 29/08/2024
When a work order (WO) is in a state that allows to record costs, it is possible to record material consumption.
However, before registering, you should note that:
- it is only possible to register consumptions if the WO status allows cost registration;
- it is only possible to select warehouses from the company for which it was registered in the requisition;
- it is only possible to register a quantity equal to or less than the one selected in the Requisition.
- the Workshop manager to whom the WO belongs can create, edit, and delete logs by the technician;
- with the Technician profile, if the warehouse has access restrictions, when adding a part to the requisition only the warehouses without access restrictions and those to which the technician in question has access are displayed.
To report material consumption, follow these steps:
- Go to Work | Work Orders;
- Select the WO for which you want to log the costs;
- In the Operations button, select the Consumptions option;
- In the list of consumption logs associated with the WO, click on Copy from Requisitions;
- In the list of requisitions per requisitioned part, select the parts to record consumption;
- Click on Create Consumption;
- By default, the Equipment, Tool, or Location fields are filled in with the WO's asset;
- If the WO is for a Route, choose the asset category and fill in the corresponding asset;
- Validate the remaining data automatically filled in;
- Click on Save.
Bookmark or share this article