How do I report consumptions using a requisition associated with the work order?

Last changed in 29/08/2024
This article applies to:
PT
ES
AO
CV
MZ
ST
GW

When a work order (WO) is in a state that allows to record costs, it is possible to record material consumption.

However, before registering, you should note that:
  • it is only possible to register consumptions if the WO status allows cost registration;
  • it is only possible to select warehouses from the company for which it was registered in the requisition;
  • it is only possible to register a quantity equal to or less than the one selected in the Requisition.
  • the Workshop manager to whom the WO belongs can create, edit, and delete logs by the technician;
  • with the Technician profile, if the warehouse has access restrictions, when adding a part to the requisition only the  warehouses without access restrictions and those to which the technician in question has access are displayed.
To report material consumption, follow these steps:
  1. Go to Work | Work Orders;
  2. Select the WO for which you want to log the costs;
  3. In the Operations button, select the Consumptions option;
  4. In the list of consumption logs associated with the WO, click on Copy from Requisitions;
  5. In the list of requisitions per requisitioned part, select the parts to record consumption;
  6. Click on Create Consumption;
  7. By default, the Equipment, Tool, or Location fields are filled in with the WO's asset;
  8. If the WO is for a Route, choose the asset category and fill in the corresponding asset;
  9. Validate the remaining data automatically filled in;
  10. Click on Save.